The 2016 Bond: What Your Money Is Doing

From the office of the Operations Division: 

In an effort to keep the community informed we would like to give you a brief update on where we are with the 2016 Bond projects. Currently, the Board of Trustees has approved the architect firm for the Escondido North Elementary site school design. A survey to the communities of Rolling Meadows and Copperfield Elementary schools will be sent out by the principals of those campuses to solicit input. We are under current negotiation with the architect to change the design in areas that need improvement based on faculty and community input. 
 
Architectural rankings for selection of the Kirby and Kitty Hawk Middle School renovations and the building of Wortham Oaks elementary site have been completed and will be presented to the Board of Trustees for review and approval in December 2016. Once the board has approved the ranking of the architectural firms for these projects, we can begin negotiations for project designs. After the designs are completed for all of these projects, construction companies will submit proposals, and construction begins afterwards.  The estimated completion of construction for the Escondido North and Wortham Oaks elementary sites will be August 2018 - December 2018. Anticipated completion of the Kirby and Kitty Hawk Middle School renovations would be in December 2019 - May 2020.

In addition, construction phases are just about to launch for the security vestibules located at Elolf and Hopkins Elementary Schools and the bidding process has started for the minor renovations planned to the existing Judson High School Agriculture Complex.

 

Comments

1
Jorge Topete

When will our district fix the parking lot at JHS's stadium?
The parking lot has been in horrible condition and it does not match the beautiful stadium we have.

2
Steve Linscomb

The parking lot is one of the projects slated from the 2016 Bond that was passed. That project is scheduled for the summer of 2017 when it does not see so much use. It should be ready before the next football season.